Water
Rising Main Installation on the Thames Water Network
Delivered for MGroup Water, supporting LOT 4 developer activities on the Thames Water network.
600m
OD350 PE100 SDR11 rising main
6
Chambers & manholes constructed
Zero
Utility strikes
Zero
Safety incidents
What We Delivered
Installation of approximately 600 metres of OD350 PE100 SDR11 rising main, predominantly by open-cut excavation, with 2 air valve chambers, 1 access chamber, 1 washout chamber, 1 break chamber and a new manhole constructed over an existing live sewer to connect the rising main into the network. The scope also includes deep excavation and gravity sewer installation requiring temporary works for safe access.
Programme Performance
2 weeks → 4 days
A gravity sewer installation at a depth exceeding two metres, programmed for two weeks, completed safely in four days.
3 weeks → 8 days
A programme-constrained activity allowed three weeks, completed safely in eight days.
Mobilisation
The project was awarded six days before we mobilised and began excavation.
Standards & Controls
Delivered to project-specific requirements, specifications and safe systems of work for the client and the Thames Water network. Known services are exposed by vacuum excavation. Where services are expected but cannot be accurately located, vacuum excavation is used to investigate to a depth of at least one metre before conventional excavation.
Why We Are Lower Risk
Controlled delivery rather than transferring risk to site teams. Our productivity has been achieved without reducing excavation or safety controls.
Safe delivery. Efficient programme performance. Protection of existing infrastructure.